The Salix Bid to replace LED lighting was carried out by PP Electrical over 3 phases with the final phase being carried out in the first week of the summer holidays.  The estimated annual kWh savings are 30,710kWh which is a 63% saving on the existing with a predicted annual financial saving of £4075 that will pay back the Salix Fund of £28K in 6.87 years.

New suspended ceilings, steel cross strengthening supports and redecoration was also carried out as part of the window replacement by;

SSP Ltd -Ceilings

Derek Griffiths – Decoration

Ian Gibbons – Steel Cross Supports

JPF Systems Ltd- Window Replacement

 The work has been carried out over 3 phases with the final windows being completed this half term.